When I call PreparedStatement.cancel() in a JDBC application, does it actually kill it in an Oracle database?

Please note that what I say below is based on observations and inferences of Oracle in use, and is not based on any deep understanding of Oracle’s internals. None of it should be considered authoritative.

What ninesided said in their first paragraph is correct. However, beware the test suggested. Not all long-running oracle queries are the same. It seems that queries are evaluated over two phases, first a phase that combines up sufficient data to know how to return the rows in the right order, and second a phase that returns the rows filling in the gaps that it didn’t compute in the first phase. The division of work between the two phases is also affected by the settings of the cost-based optimizer. e.g. First-rows vs All-rows.

Now, if the query is in phase 1, the cancel request seems at best to be queued up to be applied at the end of phase 1, which means that the query continues operating.

In phase 2, rows are returned in bunches, and after each bunch, the cancel command can take effect, so assuming the driver supports the command, the cancel request will result in the query being killed.

The specification for the JDBC cancel command does not seem to say what should happen if the query does not stop running, and therefore the command may wait for confirmation of the kill, or may timeout and return with the query still running.